The Broadway overpass has been a work zone since July 2023. For three years, Exit 185 has been the stretch of interstate that Bangor drivers planned around. This month that changes. MaineDOT scheduled southbound traffic to move off the temporary bridge and onto the new permanent one from October 16 to 19. Meanwhile, the next two exits north are each down to a single lane for the winter or settling into multi-year schedules of their own.
Taken together, the three projects at Exits 185, 186 and 187 work like a relay. The pressure on Bangor's stretch of I-95 is moving north toward Stillwater Avenue and Hogan Road, and MaineDOT's own schedules keep it there until 2029.
Broadway, the exit getting easier
The Broadway bridge carries I-95 traffic about 50,000 times a day. The 1960 steel girder span had been rated in "poor condition," according to the Bangor Daily News. The replacement costs more than $30 million.
The contractor, New England Infrastructure, has worked through a phased sequence. First came a temporary bridge for southbound traffic. Then the old northbound bridge was demolished and rebuilt, followed by the old southbound one. Northbound drivers moved onto their new bridge in September 2025. By September 2026, crews had paved the southbound approaches and bridge deck and were resetting the median barrier. The October 9 MaineDOT notice laid out the final southbound switch in four phases. During the ramp closures, drivers were detoured between Broadway and Exit 186 on Stillwater Avenue.
Some work still remains at Broadway. Once traffic is on the new southbound bridge, the temporary bridge comes out. Crews still have to realign the southbound ramps and rework the intersections at Broadway and Alden Street and at Broadway, Earl Avenue and Central Street. MaineDOT's project page says the work is scheduled to finish in late 2026. Its Bangor-area impacts page lists 2027. Plan for the later date and count it as a bonus if the earlier one holds.
Broadway has a second, smaller project close by. MaineDOT lists an upcoming intersection improvement with a new signal at Broadway and Stillwater Avenue, with an estimated 2026 start. It is planned as a 500-foot, one-lane work zone along a corner, with two-way traffic kept open, and its anticipated finish is fall 2026.
Stillwater Avenue, one exit up and just getting started
The Broadway detours sent drivers to Exit 186. That exit has its own crew now. Cianbro of Pittsfield began clearing the median there in April under a $53,820,000 contract. That contract also covers the Kenduskeag Avenue bridge, which comes up again below.
The two I-95 bridges over Stillwater Avenue date to the 1960s and are nearing the end of their service life, according to the design firm, Mott MacDonald. One single-span bridge replaces both. The design also adds height over Stillwater Avenue and widens the avenue below for a center turn lane.
Stillwater won't follow the Broadway playbook. Instead of a temporary bridge, through traffic shifts onto a median crossover that uses the new northbound alignment. MaineDOT says there will be delays but no extended detours, and that access to businesses and the pedestrian path will stay open throughout. Expect intermittent nighttime lane closures, short full closures of I-95 and Stillwater Avenue, and up to three weekend closures of Exit 186. MaineDOT has not yet posted dates for those weekend closures. In its March project announcement, the department says traffic updates will come through local media, its Facebook page and roadside message boards. The listed finish is 2029.
Hogan Road, where the winter pinch sits
Exit 187 is the busiest of the three. MaineDOT counts about 35,000 vehicles a day through the Hogan Road interchange and calls it Maine's busiest diamond interchange. The department also recorded 94 crashes there in the latest three-year period. CPM Constructors of Freeport started work on April 20, 2026. The contract totals $56,651,028.90, with support from a federal RAISE grant.
This winter's driving conditions, according to MaineDOT's project page:
- Southbound I-95 is down to one lane under Hogan Road through the winter.
- Northbound I-95 drops to one lane under Hogan Road in October and stays that way through the winter.
- Hogan Road itself sees occasional minor daytime lane closures.
- Bangor Mall Boulevard has directional boring at its entrance near Staples.
- Rolling roadblocks let trucks into the work zones in both directions.
Exits 186 and 187 sit about a mile apart. This winter one has single-lane interstate in both directions, and the other has night and weekend closures still to be scheduled. The Broadway detour route depended on Exit 186. Over the next few years, Stillwater Avenue and Hogan Road become the stretch where the planning happens.
The finished interchange will feel different. According to the Bangor Daily News, the design eliminates left-hand turns off the highway, and drivers heading onto I-95 north or south will no longer wait at stop lights. Its two crossover lanes will have drivers stop before continuing east or west on Hogan Road. MaineDOT expects the design to cut crashes by roughly half. It also adds a protected bike and pedestrian path across the interstate, where today there is no sidewalk or adequate shoulder.
The new bridge comes first. It is going in south of the existing two, and MaineDOT says most traffic patterns stay as they are until that bridge is done in late fall 2027. The project also rehabilitates the existing eastbound Hogan Road bridge and removes the westbound one, with the full interchange expected to be complete by fall 2029.
By September 2026, concrete work on the first abutment was complete. Pile work was continuing at Piers 1 through 3, and the lower half of Ramp B had been raised to its new grade.
The corridor on one calendar
| Exit | Project | Start | Contractor | Listed finish |
|---|---|---|---|---|
| 185 | I-95 bridges over Broadway | July 2023 | New England Infrastructure | Late 2026 or 2027, depending on the MaineDOT page |
| 185/186 | Broadway and Stillwater Ave signal | Estimated 2026 | Not listed | Fall 2026 |
| 186 | I-95 bridges over Stillwater Avenue | May 2026 | Cianbro | 2029 |
| 187 | Hogan Road diverging diamond | April 2026 | CPM Constructors | Fall 2029 |
Read across the rows and the pattern is clear. The oldest project is the one wrapping up. The two newest started a month apart this spring and finish in the same year. Whatever relief Broadway brings this winter is local to the south end of the corridor.
Downtown has its own dig, on a shorter clock
Away from the interstate, the City of Bangor and the Bangor Water District are working through a $2.8 million project on Cumberland Street. Crews are replacing sewer, laying new storm drain and installing water pipe. The new 24-inch water main replaces a 20-inch cast iron main built in 1897. That old main is the primary feed for the Thomas Hill Standpipe. Separating the sewer and storm lines is part of the city's consent decree commitment with the federal Environmental Protection Agency on combined sewer overflows.
The city's closure notice scheduled the Harlow Street closure at Cumberland to run from September 21 to about October 12. Drivers heading downtown were routed via Kenduskeag Avenue and Curve Street, and drivers leaving downtown were sent to Spring Street. Cumberland itself stays closed into early December. It remains open to local business and residential traffic, with workers on site to help with access. The work also reaches Harlow Court, Market Street and the Center Street intersection. The short cut-across from Market to Cumberland in front of the Attic thrift store is being removed. The city expects utility work to wrap up by December, with full reconstruction of Cumberland, including pavement and sidewalks, in early summer 2027. One phase ends by December, and the next is already on the 2027 calendar.
The 2027 closure that isn't on the interstate
The Cianbro contract covering Stillwater also includes Kenduskeag Avenue. That bridge will be replaced with a shorter span that has more clearance underneath. MaineDOT chose to close it completely to shorten construction, and the closure is expected to last about eight months starting in 2027. The detour runs about three miles via Valley Avenue. Cianbro is set to begin safety improvements on that detour route later this year.
That puts 2027 in sharper focus. Broadway should be finished by then, and the Hogan Road traffic patterns are expected to hold until the new bridge opens late that fall. The new piece will be a full closure on Kenduskeag Avenue, with a detour route that's being prepared now.
If you're weighing a sale, a purchase or simply a new commute anywhere along this corridor, Catharine Icenogle Baldwin and the Aimi Baldwin Real Estate team keep these construction calendars in view, so you'll know which roads will be open and when you plan your move. Request a Free Home Valuation and we'll show you how your address fits into Bangor's next few construction seasons.